Choose the completion status for an ad hoc report

You can specify a range of completion dates to include only content that was completed within the range of dates in a report.
  1. On the Report Filters - Step 4 of 4 screen, in the Completion Date section, perform one of the following tasks:

    Task

    Steps

    Include all completion dates.

    1. Select the All option.

    Choose a range of completion dates.

    1. Select the Range Between option.
    2. In the Start field, type a month, day, and year, or click the calendar icon and select a date.
    3. In the End field, type the month, day, and year or click the calendar icon and select a date.
  2. Click Run Report.

Was this information helpful? Send us your comments.